Building Your Own Home: Request Your Hydro-Québec Connection Early
Building your own house or cottage? Think about the electrical connection as soon as you buy the lot or get your permit, not at the end of the project. Hydro-Québec does not connect a new home automatically: your master electrician must send it a service request, and the wait can be long.
How long is the wait?
Hydro-Québec publishes a tool that estimates the lead time by postal code and lot. For a 200-amp-or-less home in Delson, in November 2026, the tool shows:
- 10 to 15 business days if the house is on the same side of the street as the poles and wires, less than 30 metres from the grid, with no change to the grid;
- 6 to 10 months if the connection requires a grid extension, for example when the grid does not reach your lot.
These lead times are estimates: they vary by region and with Hydro-Québec’s technical review. Check yours with your postal code on Hydro-Québec’s website.
What makes it longer
- no electrical grid near the lot;
- an underground service, whose civil works must be completed before Hydro-Québec’s work;
- an incomplete request, or changes made along the way;
- permits to obtain: easements, municipal approvals, environmental certificates;
- poles to plant, trees to trim or land to clear;
- an installation that is not compliant or not ready on the day Hydro-Québec comes.
The steps, in order
- At the start of the project, hire a master electrician who is a member of the CMEQ. They check the distance to the grid, the side of the street and the capacity you need.
- Gather your documents: site plan, lot plan (cadastre extract), easements and the list of equipment to connect (heat pump, EV charger, spa…).
- The master electrician sends the service request. Hydro-Québec gives you a confirmation number to track the request online.
- Power on site: if needed, we install a temporary electrical service to run your tools during construction.
- Final connection: once the installation is complete and compliant, the master electrician notifies Hydro-Québec, which connects and energizes the service.
Plan for the fees
A line extension or modification can involve fees charged by Hydro-Québec. Your electrical contractor must warn you about them: ask for an estimate before signing. Hydro-Québec also offers a cost estimation tool.
Our advice
Choose your service capacity with the future in mind: an EV charger or heat pump added later may require redoing the service entrance. And file the request as early as possible: Hydro-Québec’s lead time adds to your schedule.
Source: Work requests: steps, lead times and fees (Hydro-Québec, in French), estimation tool consulted on November 20, 2026. Actual lead times are confirmed by Hydro-Québec after reviewing your request.